The terms and standards that recur across the other clauses, with what each one actually governs.

EntriesFifteen
ScopeUK
Last checked13 September 2026

7.1Terms and standards

TermWhat it is
apparent powerMeasured in VA. The specification limit is 800 VA. Not the same quantity as the 800 W rated AC output in the instrument.
BS 1363The British Standard for 13 A plugs and socket outlets. Its prohibition on using plugs to connect generating equipment is what blocked plug-in solar until 2026.
BS 7671Requirements for Electrical Installations, the IET Wiring Regulations. Currently BS 7671:2018+A4:2026. A paid standard.
BS EN 62109-1Safety of power converters for use in photovoltaic power systems. Clause 7.3.8 governs DC residual current.
curtilageThe land attached to a dwelling. Relevant because permitted development covers buildings within it.
DESNZDepartment for Energy Security and Net Zero. Publisher of the Interim Product Specification.
DNODistribution Network Operator. Owns the local network. Not your energy supplier. Fourteen licence areas in Great Britain.
ESQCRElectricity Safety, Quality and Continuity Regulations 2002. Amended by SI 2026/848 for Great Britain.
final ring circuitThe domestic ring main. The specification limits one device per final ring circuit; G98 is tighter at one per household.
G98Engineering Recommendation for connecting fully type tested micro-generators up to 16 A per phase. Great Britain only.
G98/NIThe separate Northern Ireland connection requirements.
IP55Ingress protection rating. Required for a socket outlet mounted external to the premises.
ordinary personA person who is neither skilled nor instructed in electrical terms. The specification is written for installation by ordinary persons.
permitted developmentDevelopment allowed without a planning application, subject to conditions. Plug-in solar relies on the microgeneration solar PV rights.
PSSRPlugs and Sockets etc. (Safety) Regulations 1994. Amended by SI 2026/848.